As our work comes to an end on the Farringdon Crossrail project, some of our Partners: Gerald Skalla, Thomas Schwind and Christian Karner paid a visit to the construction site.
After 2 years and 7 months, circa 1,000m of SCL tunnels, 100,000m³ of sprayed concrete and 16 Dr. Sauer and Partners staff members from 8 countries, Dr. Sauer & Partners completes its SCL works at Crossrail’s Farringdon Station. To mark this momentous event, some of the Partners donned their hard hats and high-vis clothing and paid a visit.
In the images below you can see;
Gerald, Christian and Thomas - taking a final view from above after a visit to the Farringdon station tunnels:
Gerald, Christian and Thomas reviewing the latest RES sheet:
With Crossrail's Hugo Dickson - looking pleased at a job well done, and off to new ventures!