| Owner: | |||||
| Client: | |||||
| Service: | Advice and Recommendations for Experimental Investigation Section.
|
||||
| Estimated cost: | Commencement: | November 30, 1990
|
Completion date: | December 31, 1991
|
|
| Location: | Venezuela
|
||||
| Technical data: | 24.4 km long transfer tunnel, 4.2 m diameter. |
||||
| Geology description: | Phyllite, Sandstone. |
||||
| Categories: | |||||
| Service areas: | |||||
L= 24.368 m Water diversion tunnel TBM drive was stopped due to high rock pressure. One TBM got stuck and was lost.