| Owner: | |||||
| Client: | |||||
| Service: | Detailed Temporary and Permanent Lining Design, Settlement Assessment and Construction Supervision.
|
||||
| Estimated cost: | Commencement: | December 31, 1996
|
Completion date: | December 30, 1997
|
|
| Location: | Kent |
||||
| Technical data: | Approximately 14 m span twin track railway tunnel. Approximately 200m long. Using doorframe slab method. |
||||
| Geology description: | Superficial soil deposits, highly weathered Chalk and intact weak rock Chalk. |
||||
| Geology types: | |||||
| Categories: | |||||
| Service areas: | |||||
Rapid excavation of shallow cut (2m) for slab placement. Safe tunneling beneath operational highway. Minimal disruption to traffic