Owner: | |||||
Client: | |||||
Service: | Value Engineering: Design Consultant for a Mined Crossover Section
|
||||
Estimated cost: | Commencement: | March 01, 1981
|
Completion date: | June 01, 1983
|
|
Location: | Frankfurt/Main , Hesse Germany |
||||
Technical data: | 2 x 3 single track tubes with corssovers. Excavation section: 40 m² each. |
||||
Geology description: | Frankfurt Clay (silt and sand), waterbearing. |
||||
Categories: | |||||
Service areas: |
3 running tunnel each approximately 170 m long