Owner: | |||||
Client: | |||||
Service: | Geological/geotechnical consultant; preliminary, tender and detailed design; construction support and geotechnical instrumentation monitoring
|
||||
Estimated cost: | Commencement: | August 21, 1989
|
Completion date: | December 30, 1992
|
|
Location: | Bischofshofen, Salzburg Austria |
||||
Technical data: | Railway tunnel twin track, L = 320 m, Cross Section = 110 m², Excavation Sequence: Top Heading, Bench, Invert. |
||||
Geology description: | Quaternary gravel, sand and silt. |
||||
Geology types: | |||||
Categories: | |||||
Bid cost: | Final cost: | $7,800,000
|
|||
Service areas: |