Rupertustunnel

Owner:
Client:
Service:
Geological/geotechnical consultant; preliminary, tender and detailed design; construction support and geotechnical instrumentation monitoring
Estimated cost: Commencement:
August 21, 1989
Completion date:
December 30, 1992
Location:
Bischofshofen, Salzburg
Austria
Technical data:

Railway tunnel twin track, L = 320 m, Cross Section = 110 m², Excavation Sequence: Top Heading, Bench, Invert.

Geology description:

Quaternary gravel, sand and silt.

Geology types:
Categories:
Bid cost: Final cost:
$7,800,000
Service areas:
Shotcreting of canopy
Finished portal
Shotcreting of bench
Typical Tunnel Cross Section
Shotcrete Application at Bench
Shotcreting the Canopy Structure
South Portal during Construction
Steel Shutter Assembly