| Owner: | |||||
| Client: | |||||
| Service: | |||||
| Estimated cost: | $60,500,000
|
Commencement: | August 01, 1983
|
Completion date: | April 01, 1987
|
| Location: | Hannover , Lower Saxony Germany |
||||
| Technical data: | Mined railway tunnel, twin track Length = 2994 m Tunnel Area = 390,000 m3 Excavation Method: NATM Top Heading, Bench and Invert. |
||||
| Geology description: | Bunter sandstone: (claystone/sandstone) Dewatering in advance of excavation face. |
||||
| Categories: | |||||
| Service areas: | |||||
Krieberg Tunnel L= 2.994 m