Owner:
Client:
Service:
Estimated cost:
$60,500,000
Commencement:
August 01, 1983
Completion date:
April 01, 1987
Location:
Hannover , Lower Saxony
Germany
Technical data:

Mined railway tunnel, twin track Length = 2994 m Tunnel Area = 390,000 m3 Excavation Method: NATM Top Heading, Bench and Invert.

Geology description:

Bunter sandstone: (claystone/sandstone) Dewatering in advance of excavation face.

Categories:
Service areas:
Description

Krieberg Tunnel L= 2.994 m