Owner: | |||||
Client: | |||||
Service: | Design of Temporary Support
|
||||
Estimated cost: | Commencement: | May 01, 1996
|
Completion date: | December 01, 1996
|
|
Location: | London |
||||
Technical data: | Design of temporary shotcrete lining (150 mm thick) to support excavation for a perimiter r.c. beam at the base of the escape shaft piled walls. Shotcrete required to support the ground due to the foundations of a live railway viaduct located 2 m from the shaft walls. |
||||
Geology description: | Made Ground, Alluvium/Terrace, Gravels London Clay |
||||
Categories: | |||||
Service areas: |