Channel Tunnel Rail Link - Corsica Street Ventilation Shaft and Tunnels

Owner:
Client:
Service:
Design services and technical support during construction.
Estimated cost: Commencement:
August 27, 2001
Completion date:
May 27, 2002
Location:
73 Collier St
London
N1 9BE
United Kingdom
Technical data:

Main Shaft: 18 m (59 ft) dia., depth 30 m (98 ft); Inspection Shaft: 11m (36 ft) x 7 m (23 ft) elliptical, depth 10 m ; Ventilation tunnel: width: 6 m(20 ft) x height: 12 m (39 ft) elliptical.

Geology description:

London clay with sand lenses.

Geology types:
Activity:
Categories:
Bid cost: Final cost:
£110 million GBP
Service areas:
Description

The Corsica Street Ventilation Shaft comprises the permanent pressure relief and ventilation adit connecting the down line running tunnel to the shaft and temporary access adit tunnel. The ventilation adit was designed as a permanent sprayed concrete lined tunnel built in two phases: primary and secondary linings. The required watertightness was reached by staggering the joint locations between primary and secondary linings, utilising internal curing agents and steel fibres in the secondary lining sprayed concrete and injecting flexible tubes into joints of the secondary lining.

Construction site
Breakout from shaft
3D Model of tunnels and shaft
Shaft Base
Excavation of Service Tunnel
Exacvation of Cross Adit
Bench and Invert Excavation
Formwork for Final Lining
Excavation steps
Lattice Girder, Wire Mesh and Shotcrete Detail
Excavation and support steps
Shotcreting of 2nd layer
Shotcreting of 2nd layer
Lattice Girder installation
Lattice girder, wire mesh and shotcrete
Lattice girder, wire mesh and shotcrete
Block-out in shaft lining for tunneling
Block-out in shaft lining for tunneling
Block-out in shaft lining for tunneling
Excavation for the collar
Reinforcement for the shotcrete collar
Reinforcement for the shotcrete collar
Shotcreting of the collar