Sub-consultant for NATM/SEM design and waterproofing design.
Estimated cost: Commencement:
July 02, 2007
Completion date:
January 02, 2009
Location:
401 S. Jackson Street
Seattle, WA 98104
United States
Technical data:
Geology description:

The geology along the alignment consists of over-consolidated glacial clay and till with fractured zones, as well as sand and silt layers.

Geology types:
Activity:
Categories:
Bid cost: Final cost:
$1.6 billion USD
Service areas:
Construction methods:
Description

University Link is a 5km light rail extension that runs in twin-bored tunnels from Downtown Seattle north to the University of Washington, with stations at Capitol Hill and on the University of Washington campus. The twin-bored tunnels are connected with 20 cross passages. Dr. Sauer & Partners performed the temporary and final support design for the cross passages. This included the design of excavation and support measures and the development of specific ground support categories, settlement analyses, and the structural analyses of initial and permanent lining.

T Cross Passage
3D Finite Element Model