Main Menu

You are here

Tunnel Design & Specialities

Power Station Gallery, Leitzach

Client
Commencement - Services
July 30, 1978
Completion - Services
February 28, 1980
Location
Munich , Bavaria
Germany
Technical data

Power tunnel, lenght: 2300 m, diameter: 4 m, intake and intermediate shafts. Powerhouse, 20 m by 15 m in cross section, approx. 30 m deep.

Geology description

Weathered rock: soft sandstone and marl, talus material.

Geology types
Categories
Final cost
$26,000,000
Service areas
Tunnel Design & Specialities

Solb./Kriebergtunnel

Estimated cost
$60,500,000
Commencement - Services
August 01, 1983
Completion - Services
April 01, 1987
Location
Hannover , Lower Saxony
Germany
Technical data

Mined railway tunnel, twin track Length = 2994 m Tunnel Area = 390,000 m3 Excavation Method: NATM Top Heading, Bench and Invert.

Geology description

Bunter sandstone: (claystone/sandstone) Dewatering in advance of excavation face.

Description

Krieberg Tunnel L= 2.994 m

Categories
Service areas
Tunnel Design & Specialities

Rupertustunnel

Service Performed
Geological/geotechnical consultant; preliminary, tender and detailed design; construction support and geotechnical instrumentation monitoring
Commencement - Services
August 21, 1989
Completion - Services
December 30, 1992
Location
Bischofshofen, Salzburg
Austria
Technical data

Railway tunnel twin track, L = 320 m, Cross Section = 110 m², Excavation Sequence: Top Heading, Bench, Invert.

Geology description

Quaternary gravel, sand and silt.

Geology types
Categories
Final cost
$7,800,000
Service areas
Tunnel Design & Specialities
Shotcreting of canopy
Finished portal
Shotcreting of bench
Typical Tunnel Cross Section
Shotcrete Application at Bench
Shotcreting the Canopy Structure
South Portal during Construction
Steel Shutter Assembly
Completed Tunnel at South Portal

Rauheberg-Tunnel NBS (new high-speed railway line) Hannover to Wuerzburg

Service Performed
NATM design and instrumentation
Commencement - Services
June 29, 1983
Completion - Services
December 30, 1988
Location
Hannover , Lower Saxony
Germany
Technical data

Twin track railway tunnel, length 5.21 km (3.23 miles), full section of 140 m² approx. Excavation method: NATM, top heading, bench and invert.

Geology description

Lower shell limestone, higher bunter sandstone: clay and sandstone layers, high groundwater inflows of 400 l/s at the interface between the limestone and sandstone encountered.

Geology types
Categories
Final cost
$100,000,000
Service areas
Tunnel Design & Specialities
Groundwater Control

Eichbergtunnel - NBS (high-speed railway line) Hannover to Wuerzburg

Service Performed
NATM design and instrumentation
Commencement - Services
August 30, 1982
Completion - Services
December 30, 1985
Location
Frankfurt/Main
Germany
Technical data

Mined railway tunnel, twin track, L = 950 m, full section: 140m² approx. Construction method: NATM top heading, bench and invert.

Geology description

Bunter sandstone: claystone/sandstone.

Categories
Final cost
$12,500,000
Service areas
Tunnel Design & Specialities
Geological Profile and Tunnel Plan
Portal Structure
Excavation Face
Timber support_Collapse at top heading
Collapse at top heading

High Speed Rail Hannover to Wuerzburg

Service Performed
Consultant for Tunnel Design
Commencement - Services
June 24, 1980
Completion - Services
January 06, 1989
Location
Frankfurt/Main
Germany
Technical data

New high-speed rail section of 20 km length, including 5 tunnels. Total length of tunnel works is 8 km.

Geology description

Laminated rock, claystone and sandstone.

Geology types
Categories
Final cost
$120,000,000
Service areas
Tunnel Design & Specialities
Typical Twin Track Tunnel Cross Section
Typical Twin Track Tunnel

Graebnertunnel Westroehre

Service Performed
NATM Excavation and Support Design
Commencement - Services
July 01, 2001
Completion - Services
October 01, 2003
Location
Carinthia
Austria
Technical data

Two Lane Highway Tunnel Length: 7,047 ft (2,1km); Height: ~35 ft x ~29 ft; Section: ~840 ft2 (78.4m2) Excavation included 4 vehicular cross passages connecting existing east tunnel. Constructed using two headings from North (drill-blast) and South (mined-excavator); Grouted pipe arch for pre-support and rock anchors where needed.

Geology description

Difficult tunneling conditions as result of the presence of the Lavantal fault, un-favorable bedding and severe jointing of gneiss and mica schists.

Final cost
$38,000,000
Service areas
Tunnel Design & Specialities
Construction methods

Phase II - Allegheny Tunnel Traffic Relief Study

Service Performed
Preliminary tunnel improvement study including alignment and tunnel design
Commencement - Services
February 28, 1998
Completion - Services
December 30, 1998
Location
Allegheny, PA
United States
Technical data

Preliminary alignment study looking at four new tunnel options and rehabilitation of the existing tunnels. Design of two to four lane highway tunnels up to 6100 ft (1860 m) in length supported with rockbolts, reinforced shotcrete and lattice griders.

Geology description

Interbedded Shales and Sandstones with Limestone interbeds, Coal and Claystones. Decomposed to highly weathered fractured rock at the tunnel portals.

Geology types
Activity
Service areas
Tunnel Design & Specialities
Plan showing the existing topography, roads and streams along with the four Alignment Options
Profile showing the existing topography along the Red Alignment Option - Westbound Tunnel

Bluewater Quarry Haulage Tunnels

Service Performed
Detailed design and construction supervision
Commencement - Services
October 24, 1995
Completion - Services
November 29, 1995
Location
Nr. Dartford
Kent
United Kingdom
Technical data

Twin tunnels, 26 ft (8 m) span, length: 246 ft (75 m); 8 inch (200 mm) reinforced single pass shotcrete lining, 10 year design life.

Geology description

Head deposits overlying upper Chalk. Grades III/II at tunnel elevation.

Geology types
Final cost
$500,000
Service areas
Tunnel Design & Specialities
Marking of the future Tunnel Portals
Start of Excavation
Top Heading Reinforcement
Invert Reinforcement
Tunnel Portals during Excavation
Muck Traffic
Top Heading Final Lining
Installing of wire mesh
Preparation of portal
Fixing of reinforcement in invert
Top Heading excavation

Southwick Hill Tunnels

Service Performed
Feasibility study for NATM alternative construction, design safety checks, specialist NATM consultant for construction
Commencement - Services
December 29, 1992
Completion - Services
December 29, 1994
Location
Brighton
United Kingdom
Technical data

Two road tunnels, dual carriageway, length of 1,280 ft (390 m) each.

Geology description

Upper Cretaceous Chalk

Final cost
$10,000
Service areas
Tunnel Design & Specialities
Reinforcement, L.G. and wire mesh
Canopy, shotcrete portal
Typical Cross Section
Portal Structure and Start of Excavation
Shotcrete Application for Face Stabilization
View of Excavation Face showing Support Works

Pages