Main Menu

You are here

Waterproofing & Water Control

Lonquimai Tunnel

Service Performed
Rehabilitation design
Commencement - Services
October 22, 2001
Completion - Services
October 22, 2003
Location
Temuco
Chile
Technical data

The 4500 m (14,760 ft) long Lonquimai Tunnel is a one lane, concrete lined road tunnel. The rehabilitation design foresees to line 3500 m (11,500 ft) of the tunnel with a flexible waterproofing membrane protected by a 5 cm (2 inch) thick shotcrete shell and the installation of a new drainage system.

Geology description

Hard rock

Geology types
Final cost
$1,800,000
Service areas
Rehabilitation & Tunnel Widening, Waterproofing & Water Control
Tunnel Portal
Existing Tunnel Condition
Deterioration by Water Inflow

Lehigh Tunnels

Service Performed
NATM design, instrumentation and construction supervision services; waterproofing system design and rehabilitation support services.
Commencement - Services
March 25, 1987
Completion - Services
December 25, 1991
Location
Route 283, Eisenhower Blvd
Allentown, PA 17034
United States
Technical data

New highway tunnel, two lanes, 28 ft (8.5 m) x 40 ft (12.1 m) x 4,265 ft (1300 m). Constructed using NATM with drill and blast excavation measures. Installation of PVC membrane and thermal insulation in air duct of the 50 year old, two lane road tunnel during rehabilitation. Tunnel lenght: 4,138 ft (1260 m); waterproofed area: 117,000 sqft (10870 m²).

Geology description

Sandstone, shale, siltstone.

Geology types
Description

The Lehigh Tunnel No.2, part of a 4-lane motorway running East-West through Pennsylvania, was one of the first tunnels in the US built using NATM. Capacity problems of Lehigh Tunnel No.1 caused delays during peak times. The new tunnel was excavated using top heading, bench and invert excavation with shotcrete support. To achieve a completely dry tunnel a PVC membrane was installed between primary shotcrete lining and the final cast-in-place lining. Tunnel rehabilitation including the installation of a PVC membrane and thermal insulation in the air duct was performed to the original tunnel.

Activity
Final cost
$25,000,000
Service areas
Rehabilitation & Tunnel Widening, Waterproofing & Water Control
Ventilation duct with ice build-up
Installation of waterproofing system
Typical Cross Section
View of exisiting Tunnel Portal
Preparing Tunnel Portal to start Excavation
Tunnel Face with Shot Holes ready to blast
Formwork for Cast-in-Place Final Lining
Final Lining and Invert Drain Trench
Lehigh Tunnel No. 2 - Completed Southbound Portal
Lehigh Tunnel No. 1 - before Rehabilitation
Frozen Water Leakage in Upper Air Duct
Drainage
Lehigh Portals Tunnel No. 1 (left) and the new Tunnel No. 2
Preparations
Spiles and anchor
Spiles and anchors
seeping water
Profile check
Carrier
Essembling the formwork
Incident doing form essembling
Glossy tunnel walls
Glossy tunneling
Finished tunnel
Reinforcement of roadway
Pipes
Northportal
Lehigh Tunnel #1 & #2 South Portal
Project number
115D
Final cost
$25 million USD

Washington Dulles Airport Pedestrian Walkback Tunnel

Service Performed
Final design including FEM structural calculations.
Commencement - Services
February 01, 1998
Completion - Services
December 01, 2001
Location
45045 Aviation Drive
Dulles, VA 20166-7528
United States
Technical data

Pedestrian Walkback tunnel, accommodating two moving and one central fixed walkways, 770 ft long, Section of 41 ft x 27 ft. A Mechanical Room with a 37 ft long x 32 ft. span . Tunnel passing 15 ft beneath the main airport taxiways.

Geology description

Residual soils, decomposed rock and siltstone bedrock.

Geology types
Description

An extensive underground people-mover train system and a fixed walkway tunnel between terminals are central to a multi-phased mega program of modernization and expansion for the Washington Dulles International Airport. The pedestrian walkback tunnel, a part of the expansion plan, crosses below two airport taxilanes and will connect the Main Terminal with Mid-Field Concourse B. The tunnel was designed as a multiple-drift NATM excavation, whereby cover beneath the taxilanes was less than a tunnel diameter at only 4.5 m. Excavation was therefore designed as a very controlled sequence with top heading excavation further divided into two side drifts.

Activity
Categories
Final cost
$13,000,000
Service areas
Construction methods
Max Overburden
Min:10 Max:20
Max Excavation Area (m2)
Min:1200 Max:1200
Tunnel length
Min:770 Max:770
Walkback tunnel cross section
Access shaft and portal under taxilane
The new tunnel in relation to the airport taxiways
Excavation of Access Shaft
View from Portal to Main Terminal Building
Excavation of Connector Shaft at Junction to Walkback Tunnel
Roadheader entering the Tunnel
Access Tunnel Walkback Tunnel Junction
Access Tunnel Walkback Tunnel Junction
Walkback Tunnel Shotcrete Canopy
Flexible Membrane Waterproofing System applied to Tunnel Invert
Installation of Waterproofing System in Connector Shaft
Fixing of Waterproofing Membrane
Completed Shotcrete Final Lining
Shotcrete canopy, girder erection
Shotcrete Arch - South
Shotcrete Arch - South
Hanging Steel Mesh
Hanging Steel Mesh
Hanging Steel Mesh
Girder completly installed
Shotcrete canopy completed
Project number
207D
Final cost
$13 million USD

Pages