Main Menu

You are here

Rehabilitation & Tunnel Widening

Whiteball Tunnel - CAT3 Check Phase 2B Refurbishment

Owner
Service Performed
Independent design check (CAT 3) of phase 2B refurbishment of the Whiteball tunnel that comprises SCL lining protecting the existing brick lining.
Commencement - Services
April 01, 2019
Completion - Services
July 01, 2019
Location
Whiteball
Somerset
TA21 0LS
United Kingdom
Description

1km rail tunnel named after the nearby village of White Ball built by Brunel (opened 1844 on the Great Western Main Line). Victorian brick-arch lining, which has deteriorated over the years including weathering and chemical reaction from the sulphurous steam trains. A refurbishment scheme was required to make it fit for purpose which was planned through various phases. The early phases of the project involved installation of the RAM Arch System and wire mesh to prevent loose bricks from falling on to the tracks. In latter phases of the refurb - the subject of the CAT3 check - sprayed concrete applied to cover the RAM Arch system coupled with rock bolts with butterfly plates were used to hold the concrete lining.

Activity
Categories
Service areas
Rehabilitation & Tunnel Widening, Tunnel Design & Specialities
Whiteball Tunnel Refurbishment Plan
Whiteball Tunnel Refurbishment
Project number
520C
Project Type
Final cost
£15 million GBP

Puerto Suello Hill Tunnel

Service Performed
Tunnel inspection, structural analysis and assessment, recommendations and concepts for tunnel repair and retrofit.
Commencement - Services
April 01, 2010
Completion - Services
July 01, 2015
Location
San Rafael
San Rafael, CA 94901
United States
Geology description

The bedrock in the project area primarily comprises intact metamorphosed sandstone (i.e. graywacke) of the Franciscan Melange and contains few discontinuities. The bedrock is typically overlain by stiff to hard lean clay.

Geology types
Description

The Puerto Suello Tunnel is a 400 m long single-track rail tunnel in San Rafael, California and was constructed in 1879. The 4.9 m wide and 6.8 m high tunnel was partially destroyed by a fire in 1961, was rebuilt for freight service in 1967 and closed in the mid-1980s. The tunnel was acquired by SMART in 2003, who retrofitted and then reopened it for commuter rail service in 2017.

The ground overburden above the tunnel reaches a maximum of 45 m and the tunnel was constructed using cut-and-cover and mined construction methodologies.

Activity
Service areas
Inspection & Maintenance, Rehabilitation & Tunnel Widening
Construction methods
Puerto Suello Hill Tunnel reopened in 2017 (www.wikipedia.org)
One of the developed repair options
Project number
429C
Project Type
Final cost
$3 million USD

Reshen Kalimash Motorway Project

Service Performed
Dr. Sauer & Partners in joint venture with iC Consulenten provided mitigation and tunnel stabilisation as well as NATM redesign following a tunnel collapse.
Commencement - Services
November 01, 2009
Completion - Services
July 01, 2010
Location
Sami Frasheri No. 33
Tirana
Albania
Geology description

The geological setting is influenced by the Alpine geosyncline resulting in a complex tectonic behaviour of a variety of igneous and metamorphic rocks cut by major fault zones.

Geology types
Description

A major collapse during construction of the Thierre Tunnel in 2009 led government officials to call on NATM experts to come up with an innovative fix for the 5.6km, two-lane twin tunnel, which is part of the new Reshen Kalimash Motorway. Recommended stabilisation measures by the Dr. Sauer/iC JV such as backfilling, ribs and fibre shotcrete were implemented and halted creep movements. An alternative design was developed and replaced the original horseshoe profile by an ovoid shape. Pre-treatment, excavation works and support installation were accompanied by extensive monitoring.

Activity
Final cost
$1,000,000,000
Service areas
Rehabilitation & Tunnel Widening
Construction methods
Tunneling under
Stabilisation measures: Backfill and fibre shotcrete "egg"
Ovoid shape emerging from horseshoe profile
Project number
428E
Final cost
$1 billion USD

Felbertauern Road Tunnel

Service Performed
Consultant, rehabilitation design, supervision of rehabilitation work
Commencement - Services
December 30, 1989
Completion - Services
December 30, 1991
Location
Lienz , Tyrol
Austria
Technical data

Road tunnel 2 lanes, L = 5180 m (17,000 ft), cross section 70 m² (750 sqft) approx. The tunnel entrances are located approximately 1650 m (5,410 ft)a.s.l.

Geology description

Gneiss, amphibolite, amphibolite schists, schist (green schist).

Geology types
Final cost
$3,500,000
Service areas
Rehabilitation & Tunnel Widening
Tunnel after Rehabilitation
Inspection of Old Tunnel
Tunnel before rehabilitation
Tunnel after Rehabilitation
Rehabilitation Concept
Tunnel before Rehabilitation
Tunnel after Rehabilitation

East London Line - Brunel Thames Tunnel Refurbishment

Service Performed
Design of tunnel refurbishment including waterproofing; construction supervision
Commencement - Services
August 27, 1995
Completion - Services
October 19, 1997
Location
30 The South Colonnade
London
E14 5E4
United Kingdom
Technical data

Twin arch tunnel, 375 m (1230 ft) in length, with cross passages every 5.5 m (18 ft).

Geology description

The tunnel is covered by the Thames river bed sediments, water saturated silt, clay and sand or a suspension thereof and even partially exposed to the river water.

Description

The brick lined tunnel constructed by Mark Brunel between 1825 and 1841 was the first to be bored underwater using a shield and comprised a twin arch tunnel, 375m in length, with cross passages every 5.5m. The new lining has been designed to minimise the removal of existing structural brickwork and has a similar shape with cross passages to match the original tunnel. The reinforced concrete/shotcrete lining includes steel fibres to increase the strength and durability of the lining. A waterproof membrane has been installed around both tunnels and the cross passages between the structural brickwork and the new concrete lining.

Activity
Final cost
$21,000,000
Service areas
Rehabilitation & Tunnel Widening, Site Supervision & CM, QA/QC
Tunnel after Rehabilitation
Formwork and waterproofing
Old Engraving
Cross Section of refurbished Tunnel (left), original Tunnel (right)
Tunnel Portal during Construction
Partially completed Tunnel showing the structural Brick Masonry
Completed Tunnel and Cross Passage Linings prior to Installation of the Services and Track Works
Early Construction Stage - Installation of the Tunnel Invert Waterproofing System
Installation of the Tunnel Invert and Track Slab Reinforcement
Preparing Tunnel Roof for Waterproofing System
Steel Archs Tunnel Support
Final Cast-in-Place Lining Process
Before Rehabilitation - Cross Passages with the architecutal Features partially eroded away
Partially finished Final Lining
After Rehabilitation - The architectural Features shown were cast-in-place as Part of the Tunnel Final Lining
Reinforcement and Waterproofing at the Invert
Tunnel before Rehabilitation
Cross Passage before Rehabilitation
Cross Section
Inner Lining and Water Proofing
Project number
233
Final cost
£21 million GBP

Berry Street Tunnel

Client
Service Performed
Value engineering design and construction supervision
Commencement - Services
September 27, 1996
Completion - Services
December 28, 1997
Location
Pittsburgh, PA
United States
Technical data

Enlargement of a 2,800 ft (853 m) long, two laned brick lined tunnel to a 34 ft (10 m) wide horseshoe shaped tunnel with approx. 150 ft (46 m) of overburden. Primary lining: steel fibre reinforced shotcrete and lattice girders. Waterproof membrane with an unreinforced concrete secondary lining.

Geology description

Medium hard to soft sandstone and shale with thin beds of coal and claystone, non-cohesive fill of the original cut and cover section.

Geology types
Description

The original tunnel was built in 1865 as a 12 ft wide (4 m) single-track rail tunnel. It was widened in 1873 to 25 ft (8 m) double-track with a 26 in-thick (66 cm), brick-lined horseshoe design. After several structural repairs, mainly for spalling bricks, it was finally closed in the early 1960s. More than 30 years later the Port Authority of Allegheny County saw benefits in adapting the former railroad alignment and right of way to its new bus way connection between downtown Pittsburgh and the new Pittsburgh International Airport. A NATM value engineered proposal in the tunnel refurbishment contract provided US $ 2 mil cost savings compared to the original bid. The redesign was based on elevating the tunnel alignment so that the future tunnel crown could be excavated in better ground conditions and on changing the proposed horseshoe to a "rounded" cross section. This combined with the utilization of the NATM allowed a 40 % reduction in shotcrete thickness, a 22 % reduction in concrete lining thickness and the elimination of the reinforcement in the final lining. Furthermore, the NATM proposal eliminated pre-excavation grouting (200,000 bags of cement) and over 10,000 rock bolts while reducing lining thickness. During tunneling up to three headings were excavated simultaneously, one from each portal and one started within the tunnel, averaging a total excavation progress of 15.4 ft (4.7 m) /24h day. Following waterproofing, the concrete lining was completed 16 month after beginning of the reconstruction.

Final cost
$18,000,000
Service areas
Cross and Longitudinal Section
Cross Section
Southwest Portal before Rehabilitation
Hydraulic Ram removing existing Brick Lining
Voids in Tunnel Crown
Shotcrete Application after removing Bricks
Waterproofing System installed
View of the Shotcrete Canopy Section
Final Lining Shutter
Completed Southwest Portal
Lattice girder erection
Shotcreting of Canopy
Waterproofing Completed
Formwork and Carrier
Dwg./ Cross Section and Longitudinal Section
Removal of the Existing Brick Lining
Southwest Portal Completed
Rebar Spiling at Crown
Instalation of Rockbolts
Cross Section, Geology, Overbreak
Cross Section, Overbreak
SFR Shotcrete, Rock Dowels
Canopy,Lattice Girders, Shotcreting
Final Lining, Cast in Place

Bergen Tunnel Rehabilitation

Client
Service Performed
Geotechnical investigation, structural computations, preliminary rehabilitation design and supervision of rehabilitation works.
Estimated cost
$56,000,000
Commencement - Services
May 25, 2001
Completion - Services
October 17, 2002
Location
Jersey City
Jersey City, NJ 07304
United States
Technical data

Widening of a 4,300 ft (1310 m) long, 25 ft (7.6 m) wide double track, partially brick-lined railway tunnel built in the late 1800s. Excavation and support according to the principles of NATM with two support types. Flexible membrane waterproofing and cast in place final lining.

Geology description

Moderately close to closely jointed and fractured diabase; light gray to dark gray, very hard with moderate water infiltration.

Description

The Bergen Tunnel on the New Jersey Transit network is a double track, horseshoe shaped rail tunnel, built in the 1870s, passing through fractured diabase. Over time, water ingress has caused operational problems. In 2000 the owner decided to undertake major structural rehabilitation. The brick lining was stripped out and the original profile was enlarged to take a new reinforced in-situ concrete lining and drainage system. Old ventilation shafts were backfilled. Two large openings were retained for tunnel ventilation, emergency access and to house new power and electrical substations.

Activity
Final cost
$56,000,000
Service areas
Installation of membrane waterproofing system
Rehabilitated tunnel with final cast-in-place lining
Before Rehabilitation - East Tunnel
Portal Slope Stabilization
Typical Cross Section
Results of initial Blast to remove Brick Lining
Void Reinforcement
Shotcrete Robot
Final Lining Form and exposed Waterproofing System
Vent
Lettice Shotcrete
Existing bricklining
Before shotcreting
Side drain
Unsupported rock portal
Shotcrete portal
Shotcrete lining
Unsupported Tunnel wall
shotcreting
complete shotcreting
Complete shotcrete
Installtion of spiles
Spiling
Footing
complete installation
Sidedraine
Project number
265
Final cost
$56 million USD

Cameron Run Tunnel

Service Performed
Design, project management and site supervision
Commencement - Services
April 29, 1999
Completion - Services
December 30, 2001
Location
Alexandria, VA
United States
Technical data

Seven 20 ft (6 m) diameter x 200 ft (61 m) long storm water relief tunnels, running through railroad embankment with active train traffic. Removed worst deformations in original steel plate linings with hydraulic expander, re-lined tunnels with steel beams and sprayed 6 inch (150 mm) shotcrete lining.

Geology description

Railway embankment fill consisting of silt with sand, clayey sand and silty sand.

Geology types
Final cost
$3,800,000
Service areas
Rehabilitation & Tunnel Widening
Promoseq. 1 of 6
Promoseq. 2 of 6
Promoseq. 3 of 6
Promoseq. 4 of 6
Promoseq. 5 of 6
Promoseq. 6 of 6
Slide 1 of 25
Slide 2 of 25
Slide 3 of 25
Slide 4 of 25
Slide 5 of 25
Slide 6 of 25
Slide 7 of 25
Slide 8 of 25
Slide 9 of 25
Slide 10 of 25
Slide 11 of 25
Slide 12 of 25
Slide 13 of 25
Slide 14 of 25
Slide 15 of 25
Slide 16 of 25
Slide 17 of 25
Slide 18 of 25
Slide 19 of 25
Slide 20 of 25
Slide 21 of 25
Slide 22 of 25
Slide 23 of 25
Slide 24 of 25
Slide 25 of 25
Gerstgrasser Otto
Finished Tunnel Portal
Lining Expander
Invert of Completed Tunnel
Installed Steel Sets
Kurts test Baustellenschild
Expander Arm
Shotcreting of Final lining
Expander on the wheel loader
Expander
Steel Sets
Tunnel Portal after Rehabilitation
SMP, Surface Monitoring Point
SSMP, Shallow Subsurface Monitoring Point
Expander and installed steel sets
Rehabilitated tunnels
Upstream View of Tunnels prior to Rehabilitation
Tunnel prior to Rehabilitation with Timber Support
Trapped Debris due to Bracing
Temporary Dam during Construction to divert Flow
Lining Plate Expander
Lining Plate Expander moving Liner Plates back into Position
200 Tons Hydraulic Jack pushing Steel Lining Plate
Smooth Shotcrete Lining to provide better hydraulic Conditions
Monitoring Data
Upstream View of completed Tunnel Rehabilitation

A55 Penmaenbach Tunnel

Commencement - Services
October 01, 1998
Completion - Services
January 01, 2000
Location
United States
Technical data

Two-lane motorway tunnel constructed in 1935. Dims: 9.9m (32.5’) wide x 8.5m (27.9’) high Length: 685m (2,247’) Tunnel supported by rock bolts and shotcrete with final concrete inner lining. Damage Summary: Final lining cracked with areas of water seepage with fines loss through cracks at construction joints. DSC provided technical review services on remedial support measures.

Geology description

Rhyolite, scree and weathered Rhyolite at ports.

Service areas
Rehabilitation & Tunnel Widening

Pavonia / Newport Station - Rehabilitation

Service Performed
Rehabilitation design of a waterproofing system
Commencement - Services
May 30, 1999
Completion - Services
October 22, 2000
Location
Jersey City, NJ
United States
Technical data

Design of a flexible membrane waterproofing system for the stations southern arch ceiling and mechanical room. Removal of approx. 2.5 inch (64 mm) of existing Gunite ceiling. Installation of remedial waterproofing and water ingress diversion system with structural support frame covered by a 2 inch (51 mm) shotcrete ceiling.

Geology description

Not applicable to this project.

Final cost
$276,000
Service areas
Rehabilitation & Tunnel Widening, Waterproofing & Water Control
Inspection of Tunnel Lining
Coss Section
South End of Station
Column with ceiling Water Intrusion

Pages