Main Menu

You are here

Hard rock

Ottawa Light Rail Transit - Design

Service Performed
Tender design, preliminary and full detailed design including execution drawings for the mined twin track running tunnel, three mined station caverns and access shafts.
Commencement - Services
March 01, 2012
Completion - Services
July 01, 2019
Location
529 Albert St
Ottawa, ON K1R 7Z0
Canada
Geology description

The geology varied between competent limestone and fractured shale. A soft ground section included variable glacial till deposits of sand, silt and clay layers and a groundwater table close to ground surface.

Geology types
Hard rock, Soft ground
Description

Ottawa's Confederation Line runs from Tunney's Pasture in the west to Blair station in the east, is 12.5 km long and includes 15 stations. The central piece is a 2.5 km long tunnel, running under the central business district of the city, including 3 underground stations. The twin track running tunnel and 3 underground stations were designed using the mined construction method in order to minimise surface disruption. The underground stations are located adjacent to existing, sensitive and historic buildings and required detailed risk mitigation measures during design. An innovative engineering solution involving a tailor-made excavation sequence and permanent tension ties spanning the cavern was developed.

Activity
Construction methods
Tunneling under
Tunnel length
2.5km
Downtown station located between high-rise buildings
Downtown station construction sequencing including tie-backs
Cavern construction under way
Mined Caverns directly adjacent to existing basements
Special Excavation Sequences incorporating pre-tensioning
Large-Scale 3D Numerical Modelling incorporating the surroundings
Project number
123D
Final cost
$2.1 billion CAD
Completion date
Ongoing

Felbertauern Road Tunnel

Service Performed
Consultant, rehabilitation design, supervision of rehabilitation work
Commencement - Services
December 30, 1989
Completion - Services
December 30, 1991
Location
Lienz , Tyrol
Austria
Technical data

Road tunnel 2 lanes, L = 5180 m (17,000 ft), cross section 70 m² (750 sqft) approx. The tunnel entrances are located approximately 1650 m (5,410 ft)a.s.l.

Geology description

Gneiss, amphibolite, amphibolite schists, schist (green schist).

Geology types
Hard rock
Final cost
$3,500,000
Tunnel after Rehabilitation
Inspection of Old Tunnel
Tunnel before rehabilitation
Tunnel after Rehabilitation
Rehabilitation Concept
Tunnel before Rehabilitation
Tunnel after Rehabilitation

Boston Central Artery, Contract No. 95287-C11A1

Commencement - Services
December 28, 1995
Completion - Services
December 11, 2003
Location
Boston, MA
United States
Technical data

Road tunnel, 4 lanes, L = 3,940 ft (1200 m). Design of a mined solution to the engineers cut & cover tunnel design using NATM with various pre-support and groundwater cut-off measures, including barrel vaulting and cut-off walls.

Geology description

Glacial till (cohesive and granular) and weathered to unweathered argillite bedrock.

Geology Type: Hard Rock

Geology types
Hard rock
Description

Barrel Vault Method

Special Construction techniques
Cross Section MBTA Red Line Station
Cross Section and Support Measures
Proposed Cross Section near MBTA Bus Tunnel

New Studley Water Tunnel

Service Performed
NATM design, construction supervision and instrumentation
Commencement - Services
January 29, 1988
Completion - Services
December 29, 1990
Location
Birmingham
United Kingdom
Technical data

Large diameter shaft constructed using NATM for the diversion of a Water Supply Tunnel.

Geology description

Sandstone, Shale / Marl, Limestone

Geology Type: Hard Rock

Geology types
Hard rock
Categories
Final cost
$25,000,000
Shotcreting
Overview drawing
Overhead View of Shaft and Water Tunnel
British Construction Award 1989

Barrow-upon-Soar Tunnels

Service Performed
Value engineering: NATM detailed design, FEM calculation and design of waterproofing system.
Commencement - Services
March 27, 1986
Completion - Services
December 27, 1988
Location
Barrow upon Soar
Leicestershire
LE12 8GB
United Kingdom
Technical data

2 inclined transportation tunnels, length of 505 m (1656 ft) each. Under hydrostatic waterpressure, up to 55 psi for the first 300 m (984 ft) of each drift.

Geology description

River and glacial deposits, Blue Lias, limestones, Rhaetic Mudstones, Tea Green Marl, Mercia Mudstone, Tutbury Gypsum.

Geology types
Hard rock
Description

British Gypsum's operation at Leicestershire, a plaster production plant, improved infrastructure by establishing 2 new tunnels on site. Ground treatment for the control of water ingress during construction, drift excavation, final lining and a water ingress guarantee had to be taken into consideration. By applying NATM, the tunnel was excavated by roadheader and supported with lattice girders followed by shotcrete. The construction met the final water ingress guarantee by installing a PVC waterproofing membrane between the primary shotcrete lining and the final unreinforced in-situ concrete lining which is of a watertight quality in the invert.

Activity
Final cost
$4,000,000
Typical cross section
Canopy construction at portal
Project number
117D
Final cost
£4 million GBP

Wheaton Station and Tunnels

Client
Service Performed
Design of value engineering; cost proposal for contractor.
Commencement - Services
August 01, 1983
Completion - Services
June 01, 1987
Location
600 5th Street
Washington, DC 20001
United States
Technical data

Subway, 2 tubes, 1 double crossover, 5 shafts and cross adits, 1 station and 1 escalator, Length: 2 x 8530 ft., Construction method: NATM

Geology description

Quartz, diorite, micaschist, gneiss.

Geology types
Hard rock
Description

The project was part of the extension of Glenmont Route north into Maryland and included Wheaton Station and two approx. 2500 m long running tunnels as well as ventilation shafts and a cross-adit. Ilbau America, advised by Dr. Sauer & Partners, recommended changes to the existing conventional design and introduced the New Austrian Tunnelling Method (NATM), which was then used to construct the station tunnels, running tunnels and ancillary structures. The shaft at Hildarose Drive was constructed in conjunction with a large double cross-over.

Final cost
$48,000
Construction methods
Tunnel length
Max:180
Completed station platform
Installing waterproofing
Escalator shaft
Waterproofing installed
Finished Lining
Project number
083D
Final cost
$48,000 USD

Keller Springs Underpass Addison Airport Tunnel

Client
Service Performed
Preliminary design using NATM
Location
Dallas, TX
United States
Technical data

Two lane road tunnel, 1650 ft total length, NATM construction under existing runways in mixed face conditions.

Geology description

Soil, weathered and unweathered Limestone (Austin Chalk).

Geology types
Hard rock
Tunnel and road in use
 Tunnel Profile and Cross Section
Tunnel Portal during Excavation
Tunnel beneath active Runways

Berry Street Tunnel

Client
Service Performed
Value engineering design and construction supervision
Commencement - Services
September 27, 1996
Completion - Services
December 28, 1997
Location
Pittsburgh, PA
United States
Technical data

Enlargement of a 2,800 ft (853 m) long, two laned brick lined tunnel to a 34 ft (10 m) wide horseshoe shaped tunnel with approx. 150 ft (46 m) of overburden. Primary lining: steel fibre reinforced shotcrete and lattice girders. Waterproof membrane with an unreinforced concrete secondary lining.

Geology description

Medium hard to soft sandstone and shale with thin beds of coal and claystone, non-cohesive fill of the original cut and cover section.

Geology types
Hard rock
Description

The original tunnel was built in 1865 as a 12 ft wide (4 m) single-track rail tunnel. It was widened in 1873 to 25 ft (8 m) double-track with a 26 in-thick (66 cm), brick-lined horseshoe design. After several structural repairs, mainly for spalling bricks, it was finally closed in the early 1960s. More than 30 years later the Port Authority of Allegheny County saw benefits in adapting the former railroad alignment and right of way to its new bus way connection between downtown Pittsburgh and the new Pittsburgh International Airport. A NATM value engineered proposal in the tunnel refurbishment contract provided US $ 2 mil cost savings compared to the original bid. The redesign was based on elevating the tunnel alignment so that the future tunnel crown could be excavated in better ground conditions and on changing the proposed horseshoe to a "rounded" cross section. This combined with the utilization of the NATM allowed a 40 % reduction in shotcrete thickness, a 22 % reduction in concrete lining thickness and the elimination of the reinforcement in the final lining. Furthermore, the NATM proposal eliminated pre-excavation grouting (200,000 bags of cement) and over 10,000 rock bolts while reducing lining thickness. During tunneling up to three headings were excavated simultaneously, one from each portal and one started within the tunnel, averaging a total excavation progress of 15.4 ft (4.7 m) /24h day. Following waterproofing, the concrete lining was completed 16 month after beginning of the reconstruction.

Final cost
$18,000,000
Cross and Longitudinal Section
Cross Section
Southwest Portal before Rehabilitation
Hydraulic Ram removing existing Brick Lining
Voids in Tunnel Crown
Shotcrete Application after removing Bricks
Waterproofing System installed
View of the Shotcrete Canopy Section
Final Lining Shutter
Completed Southwest Portal
Lattice girder erection
Shotcreting of Canopy
Waterproofing Completed
Formwork and Carrier
Dwg./ Cross Section and Longitudinal Section
Removal of the Existing Brick Lining
Southwest Portal Completed
Rebar Spiling at Crown
Instalation of Rockbolts
Cross Section, Geology, Overbreak
Cross Section, Overbreak
SFR Shotcrete, Rock Dowels
Canopy,Lattice Girders, Shotcreting
Final Lining, Cast in Place

Combined Sewer Overflow Control Program, Project No. 4 and No. 5

Service Performed
Tunnel Expert Advice Services
Commencement - Services
August 31, 2000
Completion - Services
October 22, 2002
Location
Richmond, VA
United States
Technical data

Provided tunnel expert advice during the excavation and support of an 18 ft diameter 5,500 ft long TBM driven tunnel. Support Type A (80%) with rock bolts and Type B (20%) with ring steel and lagging. Final lining with rein-forced cast-in-place concrete.

Geology description

Light gray to medium gray slightly to moderately weathered Petersburg Granite (quartz, hornblende, biotite); dark grayish, slicken-sided Amphibolite layers (biotite, hornblende, feldspar).

Geology types
Hard rock
Categories
Final cost
$30,000,000

Pocoima Dam Spilway Reconstruction

Service Performed
Tunnel final lining alternative proposal
Commencement - Services
January 29, 2001
Completion - Services
October 21, 2005
Location
Los Angeles, CA
United States
Technical data

Tunnel widening from a 14 ft (4.3 m) to 29 ft (8.8 m) springline diameter section.

Geology description

Hard Rock

Geology types
Hard rock
Pacoima Dam
Cross Section of Spilway Tunnel

Pages