Main Menu

You are here

Design

Sound Transit Beacon Hill Station

Service Performed
Optimizing station and tunnel configurations, Interpreting geologic information, preliminary and detailed design, developing 3D Finite Element Models and performing structural and seismic design.
Commencement - Services
January 01, 2002
Completion - Services
January 01, 2009
Location
401 S. Jackson Street
Seattle, WA 98104
United States
Geology description

Beacon Hill Station is located 49 m below the ground surface in complex glacial soils with multiple groundwater horizons.

Geology types
Description

Beacon Hill Station is part of the 22.5 km initial segment of Sound Transit's Central Link Light Rail. It is located 49 m below the ground surface in complex glacial soils with multiple groundwater horizons. The project comprises deep mined station tunnels and two 1.5 km long running tunnels excavated using a tunnel boring machine. The mined station was excavated through compressible glacial soils with multiple groundwater horizons using conventional mining techniques. The access shafts and station headhouses were constructed using slurry walls and cut-and-cover techniques.

Activity
Design
Construction methods
Special Construction techniques
Tunneling under
Tunnel length
1.5km
Beacon Hill Station Layout
Tunnel Excavation under way
Project number
418C
Final cost
$250 million USD

Ottawa Light Rail Transit - Design

Service Performed
Tender design, preliminary and full detailed design including execution drawings for the mined twin track running tunnel, three mined station caverns and access shafts.
Commencement - Services
March 01, 2012
Completion - Services
July 01, 2019
Location
529 Albert St
Ottawa, ON K1R 7Z0
Canada
Geology description

The geology varied between competent limestone and fractured shale. A soft ground section included variable glacial till deposits of sand, silt and clay layers and a groundwater table close to ground surface.

Geology types
Description

Ottawa's Confederation Line runs from Tunney's Pasture in the west to Blair station in the east, is 12.5 km long and includes 15 stations. The central piece is a 2.5 km long tunnel, running under the central business district of the city, including 3 underground stations. The twin track running tunnel and 3 underground stations were designed using the mined construction method in order to minimise surface disruption. The underground stations are located adjacent to existing, sensitive and historic buildings and required detailed risk mitigation measures during design. An innovative engineering solution involving a tailor-made excavation sequence and permanent tension ties spanning the cavern was developed.

Activity
Design
Construction methods
Tunneling under
Tunnel length
2.5km
Downtown station located between high-rise buildings
Downtown station construction sequencing including tie-backs
Cavern construction under way
Mined Caverns directly adjacent to existing basements
Special Excavation Sequences incorporating pre-tensioning
Large-Scale 3D Numerical Modelling incorporating the surroundings
Project number
123D
Final cost
$2.1 billion CAD
Completion date
Ongoing

Green Park Station Upgrade

Service Performed
Tunnel and shaft design, construction support during excavation and primary lining works.
Commencement - Services
January 01, 2009
Completion - Services
May 01, 2010
Location
Piccadilly
London
W1J 7BX
United Kingdom
Technical data

Provide Step Free Access between street level and Northern, Piccadilly & Jubilee line platforms via a new ticket hall and lift system. The station, with an estimated annual use of 25 million, will thus become accessible for passengers with disabilities and reduced mobility.

Geology description

London Clay formation

Geology types
Description

Green Park tube station is a LU station situated on the north side of Green Park in central London. The station serves as an interchange between the Piccadilly, Victoria and Jubilee lines. As part of Transport for London's (TfL) investment programme, LU is implementing capacity enhancement and step‐free access (SFA) works to various stations. Dr. Sauer & Partners was responsible for the design of the primary support, i.e. sprayed concrete lining (SCL) and for providing construction support services including supervision of the excavation works and installation of the primary lining.

Activity
Design
Final cost
$9,000,000
Construction methods
Tunneling under
Max Overburden
10m
Proposed structures
Secondary lining works in the upper shaft
Project number
423
Final cost
£9 million GBP

Bond Street Station Upgrade Design

Service Performed
Design of the primary and secondary sprayed concrete linings, 3D FE modelling of all SCL tunnels including excavation steps and ground movement assessments.
Commencement - Services
January 01, 2011
Completion - Services
January 01, 2013
Location
Oxford Street
London
W1C 2HU
United Kingdom
Geology description

The tunnel horizon is generally within the London Clay formation with the lowest tunnels sitting in the Lambeth Group, where clay layers and water bearing clayey sands are inter-changing.

Geology types
Description

Bond Street tube station is a major gateway to London's West End served by both the Central and Jubilee lines. As part of the LU tube upgrade plan, the station is undergoing a major upgrade to increase capacity, improve accessibility and create interchange with the new Crossrail station. The project provides two additional escalators from the interchange level to the Jubilee line, low-level interchange route between the Central and Jubilee lines, a new step-free entrance, ticket hall and new lifts. The majority of the tunnelling works will be mechanically excavated and lined with sprayed concrete.

Activity
Design
Final cost
$150,000,000
Construction methods
Tunneling under
Max Excavation Area (m2)
15-90m2
Tunnel length
370m
3D view of proposed tunnelling and existing infrastructure
Connection chamber one
Graphic  showing split of 3D FE models
3D Graphic showing construction site and building frame used for laydown/plant
Northern Tunnels in relation to Jubilee Line platforms and Post Office Tunnel
Binocular Tunnel at Jubilee Platform level
Project number
419D1
Final cost
£150 million GBP

Tottenham Court Road Station Upgrade Design

Client
Service Performed
Design of numerous temporary sprayed concrete lined shaft and tunnel structures, and the waterproofing system for the upgrade of the existing London Underground Tottenham Court Road Station.
Commencement - Services
August 01, 2007
Completion - Services
January 01, 2010
Location
Oxford Street
London
London
W1D 1AN
United Kingdom
Technical data

Tottenham Court Road Station is a London Underground station situated in central London. The station serves as an interchange between the Central and Northern lines. Over 150,000 passengers use the station daily.

Geology description

London Clay Formation (over-consolidated, very stiff to hard clay)

Geology types
Description

Currently over 150,000 passengers use the station daily and with the completion of Crossrail in 2017, passenger numbers are expected to increase to over 200,000. The tunnels are of diameters between 4.0m and 11.0m and typically consist of a temporary sprayed concrete primary lining, a spray applied waterproofing membrane and a cast-in-place concrete secondary lining. Multiple transitions and interfaces to existing LU structures make for a challenging design and construction project under the busy streets of central London.

Activity
Design
Final cost
$480,000,000
Construction methods
Special Construction techniques
Tunneling under
Max Excavation Area (m2)
23-104m2
Tunnel length
13-104m
Overview of new tunnel works
General arrangement of sprayed concrete overbridge
Northern line concourse tunnel with cross passages
Installation of steel transfer beam
Excavation and support of Northern line concourse tunnel
Removal of existing backfilled structure
Project number
411D
Final cost
£480 million GBP

Crossrail Farringdon Station Design

Service Performed
Design of the primary sprayed concrete linings and excavation stability including depressurisation/dewatering. 3D FE modelling of all SCL tunnels including excavation steps.
Commencement - Services
April 01, 2012
Completion - Services
October 01, 2015
Location
39 Cowcross Street
London
London
EC1M 6BY
United Kingdom
Technical data

The BFK joint venture was awarded the constrction contract for Farringdon Crossrail station in 2011. BFK appointed Dr. Sauer & Partners as consultants for all sprayed concrete lining (SCL) tunnelling works prior to ring closure. 

Geology description

From the ground surface to the bedrock the geology comprised made ground, river terrace deposits, followed by London Clay, Lambeth Group formation, Thanet Sands and chalk.

Geology types
Description

Farringdon station is situated at the heart of London's rail network and will be one of its major rail interchange stations, which will link Crossrail, Thameslink services and London Underground trains. The station layout includes two ticket halls, two escalator inclines, two platform tunnels, connecting cross passages, concourse tunnels and ventilation adits. The chosen tunnelling system for Farringdon Station was sprayed concrete lining (SCL). The station comprised a total of 1km of SCL tunnels at depths of up to 35m below ground level and excavation cross-sections varying from 25m2 to 110m2.

Activity
Design
Final cost
$400,000,000
Construction methods
Tunneling under
Max Excavation Area (m2)
25-110m2
Tunnel length
1000m
General view of the Crossrail route with focus on Farringdon Station
Western ticket hall and SCL tunnels
CP1 (left), CP1-CH1 connection adit (centre) and PL2RC (right)
Plan view of the station showing the projection of the Faults at tunnel axis level and the Sand lenses
Probing in CP1
Cycle of risk reduction through the implementation of geotechnical risk management tools
Project number
222D5
Final cost
£400 million GBP

Bank Station Capacity Upgrade - Design

Service Performed
Design of tunnels and shafts (primary lining, waterproofing, secondary lining). SCL, squareworks and connections to existing assets.
Commencement - Services
August 01, 2013
Completion - Services
May 01, 2022
Location
London
London
EC3V 3LA
United Kingdom
Technical data

An important transport hub on the London Underground network, Bank Station forms an interchange between five lines. The Capacity Upgrade project comprises the construction of a new platform tunnel, associated running tunnel and step-free access provision.

Geology description

The geology is expected to comprise London Clay formation overlain by Quaternary superficial deposits comprising river terrace deposits and alluvium which are generally overlain by made ground.

Geology types
Description

Bank Station is a London Underground station located in the City of London financial district. It is a key interchange served by five lines. The Bank Station Capacity Upgrade (BSCU) aims to relieve heavy passenger congestion during peak hours for boarding, alighting and interchange. The capacity upgrade comprises the construction of a new southbound platform tunnel and associated length of running tunnel for the Northern line, connecting passageways to the existing station tunnels, and the provision of step-free access from King William Street. The total length of tunnels is 1,300m with tunnel cross sections that range from 10m2 up to 90m2.

Activity
Design
Construction methods
Tunneling under
BSCU project overview
3D render of existing and new structures
2D Phase 2 analysis for a situation where new tunnels are above the existing assets
King William Street station entrance
Location/Footprint of the proposed 3D FE models.
3D pdf cut for escalator 4, including new and existing assets upon completion
Project number
451D
Final cost
£563.8 million GBP
Completion date
Ongoing

B 27 Bypass Tunnel Oberrieden

Service Performed
Detailed design, instrumentation and construction supervision
Commencement - Services
December 28, 1990
Completion - Services
December 28, 1992
Location
Bad Sooden-Allendorf
37242 Oberrieden, Hesse
Germany
Technical data

Two lane road tunnel, 520 m length, construction techniques incl.: NATM, Doorframe Slab Method, Cut & Cover, Barrel Vault Method under existing railway embankment.

Geology description

Bunter Sandstone (sandstone, clystone), sand, clay and 120 year old railway embankment (rock fill, sand, clay, gravel).

Geology Types: Mixed Face

Description

The German Federal Railway Authority imposed high demands on safety since it did not allow for any disruption to railway traffic.

Barrel Vault Method, Doorframe Slab Method

Activity
Design
Final cost
$12,500,000
Special Construction techniques
Canopy, start of shotcrete work
Canopy, anchor beam
Installation of the Barrel Vault
Portel under construction, barrel vault completed
Doorframe slap, I-beam installation
Installation of the barrel vault
Top heading
Sidewall drift, top heading, grouting of foundation aera
Sidewall drift, grouting at invert & bench
Sidewall Dirft, Bench
Side Drift Top Heading, Break Through
Cross Section, Excavation Sequences
Side Wall Drift, Temporary Shotcrete Invert at Top Heading
Sidedrift, Top Heading, Shotcreting
Installation of the Barrel Vault, Drill
Sketch of Railway Underpass
Finished Portal
Grouting at Invert and Bench
Installed Barrel Vault
Door Frame Slab, Open Cut for Slab Preparation
Portal Preperation
Pipes isntalled
Pipes installation at T.H.
Pipes installation at T.H
Installed barrel vault
History
Barrel Vault pipe/whole through
Test
Installed
Pump utilities
Installation of Pipes
Cement for grouting
Installation of pipes
Equipment Drill Rig
Drill device
Installation of pipes
In_Situ test
Project Overview and different Construction Methods
Excavation and Support Concept
Scheme of the Doorframe Slab Method
Doorframe Slab Method
Scheme of the Barrel Vault Method
Barrel Vault at S-Portal
Barrel Vault at N-Portal
Barrel Vault Pipe Installation
Shotcrete Canopy at S-Portal
Tunnel Portal beneath Active Rail Line
Shotcrete Middlewall
Finished Tunnel

Barrow-upon-Soar Tunnels

Service Performed
Value engineering: NATM detailed design, FEM calculation and design of waterproofing system.
Commencement - Services
March 27, 1986
Completion - Services
December 27, 1988
Location
Barrow upon Soar
Leicestershire
LE12 8GB
United Kingdom
Technical data

2 inclined transportation tunnels, length of 505 m (1656 ft) each. Under hydrostatic waterpressure, up to 55 psi for the first 300 m (984 ft) of each drift.

Geology description

River and glacial deposits, Blue Lias, limestones, Rhaetic Mudstones, Tea Green Marl, Mercia Mudstone, Tutbury Gypsum.

Geology types
Description

British Gypsum's operation at Leicestershire, a plaster production plant, improved infrastructure by establishing 2 new tunnels on site. Ground treatment for the control of water ingress during construction, drift excavation, final lining and a water ingress guarantee had to be taken into consideration. By applying NATM, the tunnel was excavated by roadheader and supported with lattice girders followed by shotcrete. The construction met the final water ingress guarantee by installing a PVC waterproofing membrane between the primary shotcrete lining and the final unreinforced in-situ concrete lining which is of a watertight quality in the invert.

Activity
Design
Final cost
$4,000,000
Typical cross section
Canopy construction at portal
Project number
117D
Final cost
£4 million GBP

Pages