Main Menu

You are here

Execution

Devil's Slide Tunnels

Service Performed
Construction inspection and scheduling for initial and final liner and waterproofing; analysing monitoring data and project's progress; daily site inspection and ground conditions reports.
Commencement - Services
November 01, 2007
Completion - Services
March 01, 2011
Location
585 Linda Mar Boulevard
Pacifica, CA 94044
United States
Geology description

The geological setting comprised quartz diorite, marine sandstone, conglomerate and clay-siltstone. Four main fault zones were encountered.

Geology types
Description

Devil's Slide is located south of the City of Pacifica in California along the coastal road of Highway 1. Landslides and grade subsidence in the Devil's Slide area along Route 1 have led to the road being closed for extended periods causing significant economic loss to the surrounding communities. The solution: Construct a tunnel through the mountain to bypass the dangers and reoccurring problems. Construction of 1250m twin tunnels, 9m wide, 6.8m high using Sequential Excavation Method (SEM). Additionally, drill and blast and roadheader excavation through weathered rock utilised.

Activity
Execution
Final cost
$273,000,000
Construction methods
Special Construction techniques
Groundwater control
Max Overburden
~250m
Tunnel length
1250m
Drill jumbo drilling blast holes in top heading advance face
Finished southbound tunnel with textured cast-in-situ concrete
Tunnel Portals
Aerial view of completed portals
Project number
272E
Min Overburden
<5m at portals
Final cost
$273 million USD

Bond Street Station Upgrade Execution

Service Performed
Design of SCL tunnels and access shafts linked to Central, Jubilee line, and Crossrail Link Passage. Construction supervision.
Commencement - Services
June 01, 2013
Completion - Services
May 01, 2016
Location
Oxford Street
London
W1C 2HU
United Kingdom
Geology description

London Clay

Geology types
Description

Bond Street Station serves an interchange between the Jubilee Line, the Central Line and the future Crossrail Station. New tunnels including access and lift shafts, construction adits, binocular cross passage tunnels, large concourse and connection chambers, underpass and over-bridge tunnels cutting through existing platform tunnels, and an inclined escalator tunnel were constructed in very close proximity to existing London Underground structures.

Activity
Execution
Tunneling under
Max Overburden
10-50m
Max Excavation Area (m2)
25-55m2
Excavation connection chamber
Secondary lining escalator tunnel
SCL spray of Connection Chamber
SCL Access Tunnel
SCL Tunnel connecting to existing Cast Iron Passage Way
SCL Tunnel, Excavation of Escalator Tunnel
SCL Shaft, breakout for SCL tunnel
SCL Side Drift Tunnel
Project number
419E
Final cost
£150 million GBP

Tottenham Court Road Station Upgrade Execution

Client
Service Performed
Design of SCL tunnels and access shafts linked to both Central and Northern line. Supervision during construction.
Commencement - Services
March 01, 2011
Completion - Services
January 01, 2016
Location
Oxford Street
London
W1D 1AN
United Kingdom
Geology description

London Clay formation

Geology types
Description

The major upgrade to the LU Tottenham Court Road Station has been proposed to relieve congestion, achieve step-free access and modernise the station. The major elements of the station upgrade comprised a new enlarged sub-surface ticket hall, a fire-fighting access / emergency escape shaft linked to both Central and Northern lines, a triple escalator barrel, and concourses to the Northern and Central lines. In the latter concourse two new overbridges were included to lead to the platforms via new stairs and lifts. For the tunnelling works, a particularly challenging part was to design and construct the two SCL overbridges over the operational Central line.

Activity
Execution
Final cost
$480,000,000
Tunneling under
Max Overburden
10-20m
Max Excavation Area (m2)
23-104m2
Tunnel length
13-104m
SCL side drift tunnel
Aerial view of the construction site
Sprayed Waterproofing Membrane
SCL Crosspassage
SCL Tunnel, overbridging operational Central Line Tunnel
SCL Excavation through existing Structure
Project number
411E
Final cost
£480 million GBP

Crossrail Eastern Running Tunnels

Service Performed
Shaft and tunnel design, engineering support, geotechnical engineering and site supervision services.
Commencement - Services
February 01, 2011
Completion - Services
December 01, 2012
Location
London
London
EC1M 6BY
United Kingdom
Geology description

Geological locations of the cross passages vary from London Clay to Lambeth Group and Thanet Sands.

Geology types
Description

Contract C305 is the biggest design-bid-build construction contract of the Crossrail (CRL) project and includes the eastern running tunnels of CRL's central section with launch shafts and SCL launch adits for TBMs at Limmo Peninsula, SCL caverns and launch adits for TBMs at Stepney Green and 10 SCL cross passages between the running tunnels with lengths up to 30m. At the Limmo Peninsula site a 40m deep and 30m diameter SCL shaft was built. At the shaft bottom in Stepney Green, two 30m long and up to 10m wide SCL launch adits were constructed followed by two 14m high and up to 18m wide, SCL caverns with single sidedrift and double sidedrift cross sections.

Activity
Execution
Construction methods
Max Excavation Area (m2)
50-130m2
Tunnel length
15m
Limmo Main Shaft
Limmo Auxiliary Shaft bottom
Platform Tunnel West - Excavation - TBM Tunnel Enlargement
3D Model Limmo Auxiliary Shaft
Limmo Shafts and Tunnel layout - left Auxiliary Shaft - right Main Shaft
Project number
222E3
Final cost
£500 million GBP

Crossrail Farringdon Station Execution

Service Performed
Tunnel design, engineering support, geotechnical engineering and site supervision services were provided.
Commencement - Services
March 01, 2013
Completion - Services
November 01, 2015
Location
39 Cowcross Street
London
EC1M 6BY
United Kingdom
Technical data

Located in the heart of Crossrail, Farringdon is one of London’s major rail interchange stations, providing connections between three networks (Thameslink, Crossrail and London Underground). Dr. Sauer & Partners provided 24/7 supervision support during the SCL works.

Geology description

The majority of the tunnelling takes place within the Lambeth Group formations.

Geology types
Description

Farringdon station is now one of London's major rail interchange stations, providing connections between three networks. During the construction of the Crossrail project, it also received four earth pressure balanced tunnel boring machines (TBMs): the two Drive X TBMs, running from Royal Oak to Farringdon and the two Drive Y TBMs, running from Limmo to Farringdon. The complete station layout will comprise two ticket halls, two platform tunnels, connecting cross passages, escape and ventilation adits, two escalator - inclines and two concourse tunnels constructed using mainly SCL tunnelling.

Activity
Execution
Bid cost
$300,000,000
Final cost
$400,000,000
Construction methods
Special Construction techniques
Tunneling under
Max Excavation Area (m2)
25-110m2
Tunnel length
1000m
Western ticket hall site overview
Cross passage 3 from platform tunnel east
Platform Tunnel West - RTE2 excavation - TBM Turn and Bury
Western Ticket Hall Site Overview I
Platform Tunnel West - TBM Tunnel Enlargement
Project number
222E5
Final cost
£400 million GBP

Chinatown Station

Service Performed
Conceptual, preliminary, detailed design of underground caverns, egress tunnels and mined shafts; scheduling and cost estimating; risk management; specifications and tender. Onsite support during construction.
Estimated cost
$1,600,000,000
Commencement - Services
March 01, 2016
Completion - Services
March 31, 2018
Location
425 Market Street Suite 1700
San Francisco, CA 94105
United States
Geology description

The geology ranges from soft clay (Bay Clay) to stiff sands (Colma Sands) and competent to highly fractured rock (Franciscan Formation). The groundwater table is generally above the cavern springline.

Geology types
Description

Chinatown Station is the Northern Terminus of the Third Street Light Rail Project, which is located in a dense urban neighbourhood, underneath a busy street and directly adjacent to numerous old buildings, as well as one high-rise building. The station encompasses a Cut-and-Cover headhouse for passenger entry, three large station caverns and an emergency egress shaft. In order to minimise excavation volume and optimise cost and schedule, the ventilation ducts are located below the platform level, and routed into the headhouse.

Activity
Execution
Construction methods
Special Construction techniques
Tunneling under
Groundwater control
Tunnel length
2.7km
Excavation and support sequence of large urban cavern
Large urban cavern under construction
Excavation and support sequence - longitudinal section
Chinatown, San Francisco Dense Urban Neighborhood
Overall Station Layout, Headhouse and Caverns (Rendering by JV)
Station Cavern with Center Platform, Mezzanine and Ventilation Ducts
Proposed Mitigation Measures for adjacent Buildings
Complex 3D Finite Element Analyses
Project number
358E
Final cost
$1.6 billion USD
Completion date
Ongoing

Bergen Tunnel Rehabilitation

Client
Service Performed
Geotechnical investigation, structural computations, preliminary rehabilitation design and supervision of rehabilitation works.
Estimated cost
$56,000,000
Commencement - Services
May 25, 2001
Completion - Services
October 17, 2002
Location
Jersey City
Jersey City, NJ 07304
United States
Technical data

Widening of a 4,300 ft (1310 m) long, 25 ft (7.6 m) wide double track, partially brick-lined railway tunnel built in the late 1800s. Excavation and support according to the principles of NATM with two support types. Flexible membrane waterproofing and cast in place final lining.

Geology description

Moderately close to closely jointed and fractured diabase; light gray to dark gray, very hard with moderate water infiltration.

Description

The Bergen Tunnel on the New Jersey Transit network is a double track, horseshoe shaped rail tunnel, built in the 1870s, passing through fractured diabase. Over time, water ingress has caused operational problems. In 2000 the owner decided to undertake major structural rehabilitation. The brick lining was stripped out and the original profile was enlarged to take a new reinforced in-situ concrete lining and drainage system. Old ventilation shafts were backfilled. Two large openings were retained for tunnel ventilation, emergency access and to house new power and electrical substations.

Activity
Execution
Final cost
$56,000,000
Installation of membrane waterproofing system
Rehabilitated tunnel with final cast-in-place lining
Before Rehabilitation - East Tunnel
Portal Slope Stabilization
Typical Cross Section
Results of initial Blast to remove Brick Lining
Void Reinforcement
Shotcrete Robot
Final Lining Form and exposed Waterproofing System
Vent
Lettice Shotcrete
Existing bricklining
Before shotcreting
Side drain
Unsupported rock portal
Shotcrete portal
Shotcrete lining
Unsupported Tunnel wall
shotcreting
complete shotcreting
Complete shotcrete
Installtion of spiles
Spiling
Footing
complete installation
Sidedraine
Project number
265
Final cost
$56 million USD

Metro de Santiago, Linea 2 South Extension, Lo Ovalle to La Cisterna

Owner
Service Performed
NATM design support services and on-site monitoring.
Commencement - Services
January 30, 2001
Completion - Services
December 30, 2004
Location
Av. Libertador Bernardo O'Higgins 1414
Santiago
Chile
Technical data

2.5 km Dual Track Running Tunnels and two Stations with a maximum span of 16.2 m. Excavation of 60-65 m² running tunnel in combined top heading/bench with a subsequent invert excavation. Reinforcement consists of lattice griders and welded wire fabric for initial lining and welded wire fabric for final shotcrete lining.

Geology description

Ripio de Santiago (quaternary conglomerate) consists of a stable matrix of smooth rounded rocks held by bonding fines. Due to earthquake activity it gained compaction and interlocking.

Geology types
Description

The Santiago Metro network comprises five lines. The Linea 2 South extension included 2.5km dual track running tunnels and two stations with a maximum span of 16.2m. Further, an excavation of 60-65m2 running tunnel in combined top heading/bench with a subsequent invert excavation. Reinforcement consisted of lattice girders, welded wire fabric for initial lining and welded wire fabric for final shotcrete lining. Dr. Sauer and Partners assisted in the production of design criteria for the final design and produced finite element structural computations for the large station caverns.

Activity
Execution
Final cost
$29,600,000
Construction methods
Excavations of topheading
Shaft and portal
Side drifts, Junction station running tunnel
First side drift
Installation of lattice girder and wire mesh
Headwall
Start-up of sidewall drift
Kurt Egger
Reinforcement of headwall
Compact sand and gravel
Support beam
El Parron South
El Parron South
Sidewall drift
Face support earth wedge located in the top heading
Stress meter
Stress meter
Gerstgrasser Otto
Gerstgrasser Otto
Brunner W.
Dr.Sauer & Gerstgrasser Otto
FEM-Model of Access Tunnel - Station Tunnel Junction
Sidewall Drift Portal
Shotcrete Application
Breakout from Tunnel
Excavation of Center Drift
Demolition of Temporary Sidewall
Mucking out through Access Shaft
Linea 5 - Junction Station-Tunnel
Installation of Tracks
Completion of Electrical Installations in Station
Linea 5 - Finished Station
Excavation of invert
Project number
296E
Final cost
$29.6 million USD

Channel Tunnel Rail Link - Corsica Street Ventilation Shaft and Tunnels

Service Performed
Design services and technical support during construction.
Commencement - Services
August 27, 2001
Completion - Services
May 27, 2002
Location
73 Collier St
London
N1 9BE
United Kingdom
Technical data

Main Shaft: 18 m (59 ft) dia., depth 30 m (98 ft); Inspection Shaft: 11m (36 ft) x 7 m (23 ft) elliptical, depth 10 m ; Ventilation tunnel: width: 6 m(20 ft) x height: 12 m (39 ft) elliptical.

Geology description

London clay with sand lenses.

Geology types
Description

The Corsica Street Ventilation Shaft comprises the permanent pressure relief and ventilation adit connecting the down line running tunnel to the shaft and temporary access adit tunnel. The ventilation adit was designed as a permanent sprayed concrete lined tunnel built in two phases: primary and secondary linings. The required watertightness was reached by staggering the joint locations between primary and secondary linings, utilising internal curing agents and steel fibres in the secondary lining sprayed concrete and injecting flexible tubes into joints of the secondary lining.

Activity
Execution
Categories
Final cost
$110,000,000
Construction site
Breakout from shaft
3D Model of tunnels and shaft
Shaft Base
Excavation of Service Tunnel
Exacvation of Cross Adit
Bench and Invert Excavation
Formwork for Final Lining
Excavation steps
Lattice Girder, Wire Mesh and Shotcrete Detail
Excavation and support steps
Shotcreting of 2nd layer
Shotcreting of 2nd layer
Lattice Girder installation
Lattice girder, wire mesh and shotcrete
Lattice girder, wire mesh and shotcrete
Block-out in shaft lining for tunneling
Block-out in shaft lining for tunneling
Block-out in shaft lining for tunneling
Excavation for the collar
Reinforcement for the shotcrete collar
Reinforcement for the shotcrete collar
Shotcreting of the collar
Project number
340E
Final cost
£110 million GBP

Cumberland Gap Tunnels

Service Performed
Value engineering studies on the structural design and ventilation design; specification and on-site inspection services.
Commencement - Services
September 01, 1990
Completion - Services
December 30, 1994
Location
330 W Broadway St # 264
Tennessee, KY 40601
United States
Technical data

Twin tube highway tunnels, 12 m x 9 m x 1249 m long. Constructed using NATM support categories Type I through IV. Remedial waterproofing system installed between shotcrete linng and final cast-in-place concrete lining.

Geology description

Quartz sandstone, siltstone, shale, mudstone (natural caverns).

Geology types
Description

The Cumberland Gap Tunnels are two dual-lane highway tunnels with a length of 1300m each, connecting Kentucky and Tennessee through the Cumberland Mountains. Because of the complex, variable geology and economic considerations, the New Austrian Tunneling Method (NATM) was chosen. The tunnel design included five excavation and support classes with rock dowels, lattice girders and reinforced shotcrete as primary lining. The final lining for the twin tunnels and 13 cross passageways was designed as cast-in-place (CIP) concrete with a flexible membrane waterproofing system.

Activity
Execution
Final cost
$85,000,000
North portal
Cross passage CIP lining reinforcement and exposed waterproofing
Waterproofing System and CIP Final Lining
Tunnel Top Heading Excavation
Halmer Hans
Typical Cross Section
North Portal
Top Heading Excavation
Waterproofing Membrane and Reinforcement
Finished Waterproofing System and Final Lining
Cross Passage CIP Lining Reinforcement
oncoming traffic from manwalk in southbound tube of Cumberland Gap Tunnel. Taken in Sept 2002 by N. Wageley
Finished South Portal, Cumberland Gap Tunnels, KY/TN Taken 09-2002 by N. Wageley (film)
Project number
091E
Final cost
$85 million USD

Pages